Goldman Sachs auditorium
Commissioned by: Arminhall engineering
Main contractor: ISG
Team of: 4
Duration: 3 weeks
Target: To install steel Beams & columns to create a curved wall (Floor to ceiling) 14 meters high which would form an auditorium for Goldman Sachs International.
We erected the structure by resin anchoring the chain blocks in the ceiling, the lifting points where then pull tested to 1.2 tons to make sure the steel was safe to lift. We proceeded to fit the steel all the way round the auditorium so that they could fire board / plaster board the area once we had finished.